Which outcome is expected as Scrum Teams mature?

Which outcome is expected as Scrum Teams mature?
A. They will improve their definition of "Done" to include more stringent criteria.
B. The Sprint Retrospectives will grow to be longer than 4 hours.
C. There is no need for a time-boxed Sprint, since time-boxes are only for new Scrum Teams.
D. Sprint Reviews will no longer be needed.
E. A Scrum Master is no longer needed since they are a mature team now.

How To Pass PSM I Exam?

Scrum PSM I PDF dumps.

High quality PSM I PDF and software. VALID exam to help you pass.

How To Pass PSM II Exam?

Scrum PSM II PDF dumps.

High quality PSM II PDF and software. VALID exam to help you pass.

4 thoughts on “Which outcome is expected as Scrum Teams mature?

    1. In my opinion A is wrong, E is the correct answer.
      The Scrum Master is a facilitator, (s)he helps the Dev team(s) and the whole organization to adopt the scrum rules and best practices. When the dev teams + PO do everything so well together, they don’t need the scrum master anymore.

      1. One primary function of a Scrum Master is to remove impediments for the Scrum Team. Impediments will always be encountered regardless of how mature your Scrum Team is and it is the job of the SM to remove that.