You are using Microsoft Test Manager (MTM).
Your company no longer supports a particular configuration for the application under test.
You need to ensure that the test configuration is unavailable as an option in a test plan.
Which state should you assign to the test configuration?
A. Closed
B. Inactive
C. Disabled
D. Idle
Correct Answer: B
Explanation/Reference:
When you have completed the tests in a test plan, set its state to Inactive. This prevents more tests from being run in this plan, but still allows the results of existing runs to be viewed. When the results are no longer required you can delete the test plan.