The administrator wants to power on VM-K2, which has a 2GHz CPU reservation.
VM-M1, VM-M2, and VM-K1 are all powered on. VM-K2 is not powered on. The exhibit shows the parent and child resource reservations.
If Resource Pool RP-KID is configured with an expandable reservation, which statement is true?
A. VM-K2 will be unable to power on because there are insufficient resources.
B. VM-K2 will be able to power on since resource pool RP-KID has 2GHz available.
C. VM-K2 will be unable to power on because only 2GHz are reserved for RP-KID.
D. VM-K2 will receive resource priority and will be able to power on this scenario.