Which three actions should you perform?

Your company uses Project Standard 2013 to track project progress.
You need to accurately calculate cost performance index (CPI) as a health indicator.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A. Ensure there is a value in the Status Date field.
B. Ensure there is a value in the Standard Rate field.
C. Ensure Task Dependencies exist in the schedule.
D. Enter actual progress information.
E. Level resources within available slack.