You are utilizing the Microsoft Solution Framework (MSF) for Agile Software Development 6.0 process template.
You need to track progress for the current sprint.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A. Review team capacity.
B. From the Product Backlog view of the current sprint, review the By Work capacity bars for each contributor.
C. Review the task board.
D. Review the burndown chart.
E. From the project portal, review the Iteration Backlog spreadsheet.
Correct Answer: ADE
Explanation/Reference:
A:
The following image displays an example capacity configuration.
E: You can use the Iteration Backlog workbook to plan and track the progress of work for each iteration, also known as a sprint. This workbook calculates the team capacity and burndown based on the estimated and remaining effort defined for tasks. Note: The Iteration Backlog workbook is stored on the server that hosts SharePoint Products for your team project. If a project portal has not been enabled for your team project, you cannot access the workbook.
D: After a team has worked on one or more iterations, also known as sprints, you can determine the rate of team progress by reviewing the Burndown and Burn Rate report. Burndown shows the trend of completed and remaining work over a specified time period. Burn rate provides calculations of the completed and required rate of work based on the specified time period. In addition, a chart shows the amount of completed and remaining work that is assigned to team members. You can view the Burndown and Burn Rate report based on hours worked or number of work items that have been resolved and closed.
Example:
Reference: Burndown and Burn Rate Report (Agile): Iteration Backlog Workbook