You are using the Microsoft Framework (MSF) for Capability Maturity Model Integration (CMMI) Process Improvement 6.0 process template.
You are the scrum master.
You need to assign product requirements to an iteration.
Which three actions should you perform? (Each correct answer presents part of the solution. Choose three.)
A. Create a test harness to confirm that the business requirements are understood.
B. Find the dependencies among the product requirements.
C. Prioritize each of the requirements.
D. Create a prototype to validate whether or not the requirement can be accomplished.
E. Estimate the cost of each of the requirements.
Correct Answer: BCE
Explanation/Reference:
Assigning Product Requirements to Iterations
Representatives of the business stakeholders and the development team should work together to assign product requirements to iterations. Typically, you do this in a meeting, where you share or project the Office Excel view of the Product Requirements query. The assignment is completed by using the following pieces of information:
* Dependencies among the product requirements. In an incremental series of requirements, the simplest requirements must be tackled before enhancements in the same area.
* The priority of the requirement.
* The estimated cost. Given the number of team members and the length of the iteration, each iteration has only a fixed number of hours that are available for development. Furthermore, a significant number of those hours will be used for iteration planning and other tasks that do not directly involve development.
Reference: MSF for CMMI Process Improvement v6.0 Process Guidance