Which three actions should you perform in sequence?

DRAG DROP
You are a senior project manager in a software development company. You manage your projects with Project Professional 2013.
The development team is behind schedule due to a problem found in the architectural design of the database. The lead architect estimates that redesigning the database will take approximately 30 hours. You create a new manual task and assign it to the lead architect. However, the task has not been scheduled.
You need to easily see a time phased view of all tasks for the lead architect in order to schedule the task for completion.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
Select and Place: