Which three techniques would be most helpful in this situation?

A Scrum Master is keeping a list of open impediments, but it is growing and he/she has been able to resolve only a small portion of the impediments. Which three techniques would be most helpful in this situation? (Choose three.)
A. Consulting with the Development Team.
B. Prioritizing the list and working on them in order.
C. Arranging a triage meeting with all project managers.
D. Alerting management to the impediments and their impact.