Which tracking method should you use?

You work for an organization that uses Project Server 2013. Single-entry mode is disabled. Team members enter updates in Project Web App (PWA) through the Tasks page. You need to select a tracking method that enables the following scenario:
. During week one, a team member enters a total of 20 hours of actual work.
. During week two, the team member modifies the total to 30 hours of actual work.
. Following a save, the work value remains the same, and the remaining work value . decreases.
. Additionally, the percent of work complete increases.
Which tracking method should you use?
A. Percent of work complete.
B. Actual work done and work remaining.
C. Hours of work done per period.
D. Report hours worked every day.