Which two actions are part of the Display Connection step during endpoint configuration?

Which two actions are part of the Display Connection step during endpoint configuration? (Choose two.)
A. Determine the screen resolution.
B. Register the endpoint to Unified Communications Manager.
C. Perform an internal display cabling check.
D. Determine the system layout display on Touch 10.
E. Register the endpoint to the Cisco VCS.