Which two actions should you perform?

You are a program manager. You use Project Server 2013 and Project Professional 2013 to manage your portfolio which includes master projects and sub-projects. There is a mandatory Enterprise Custom Field called Business Unit that provides lookup values so that project managers can categorize their sub-projects. The Business Unit field has been added to all of the Project Center views. You need to show all projects within Project Center grouped by business unit.
Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
A. Make sure the Subprojects checkbox is checked in ribbon.
B. Set the Filter option to Filter by Business Unit.
C. Set the view from Summary View to the Detail View.
D. Set the Group by option in the ribbon to Business Unit.

microsoft-exams