Which two activities should you include?

You are a project manager. You are taking over a Microsoft Dynamics implementation. The project is in the design phase. You need to identify the test activities.
Which two activities should you include? (Each correct answer presents part of the solution. Choose two.)
A. create a data subset for testing
B. create system maintenance procedures
C. create system configurations
D. develop performance test scripts
E. identify process testing scenarios

microsoft-exams