Which two activities will a Product Owner engage in during a Sprint? (Choose the best two answers.)
A. Run the Daily Scrum.
B. Prioritize the Development Team’s work on the Sprint Backlog.
C. Update the Sprint burndown chart.
D. Answer questions from the Development Team about items in the current Sprint.
E. Work with the stakeholders.
Correct Answer: DE
Explanation/Reference:
How To Pass PSM I Exam?
Scrum PSM I PDF dumps.
High quality PSM I PDF and software. VALID exam to help you pass.
|
|
How To Pass PSM II Exam?
Scrum PSM II PDF dumps.
High quality PSM II PDF and software. VALID exam to help you pass.
|
|
Which one would be the best answer if you can only choose one of them?
A,B,C are not Correct, so the possible answers are D & E
agree with DE
because he is the connector to the stakeholders
because the Product owner is the link between the key stakholders and the Development team
why e
Scrum Guide “Product Owner”: