Which two items must be completed within the development phase?

You are a project manager and you are using the waterfall delivery for a project.
Which two items must be completed within the development phase? (Each correct answer presents part of the solution. Choose two.)
A. project design
B. custom coding
C. analysis phase
D. production specifications
E. design phase