Which two settings should you verify?

You are a project manager who uses Project Server 2013. You want to use the Resource Center Availability function and the Assignment Work by Resource view to see the proposed and active projects for a particular resource. However, you are only able to view part of the work load for the resource. You need to view the complete work load for the resource. Which two settings should you verify? (Each correct answer presents part of the solution. Choose two.)
A. That Include proposed bookings is selected.
B. That the units chosen are correct.
C. That the date range is correct.
D. That the resource is selected on the Resource Availability view.