Which view should you use?

Your company uses Project Professional 2013.
An organization with project managers of varying expertise wants a simple, standard view that displays overall project status.
You need an out-of-box function that provides the ability to assess current, baseline, and actual work for the project.
Which view should you use?
A. Project Overview dashboard
B. Resource Allocation view
C. Work Overview dashboard
D. Relationship Diagram view