Who is responsible for tracking the remaining work of the Sprint?

Who is responsible for tracking the remaining work of the Sprint?
A. The Development Team.
B. The Scrum Master.
C. The Project Manager.
D. The Development Team is consultation with the Product Owner.
E. The Product Owner.

How To Pass PSM I Exam?

Scrum PSM I PDF dumps.

High quality PSM I PDF and software. VALID exam to help you pass.

How To Pass PSM II Exam?

Scrum PSM II PDF dumps.

High quality PSM II PDF and software. VALID exam to help you pass.

4 thoughts on “Who is responsible for tracking the remaining work of the Sprint?

  1. According to the Scrum Guide, “The Development Team tracks this total work remaining at least for every Daily Scrum to project the likelihood of achieving the Sprint Goal”. The sprint goal tracking is by Dev team , while the goal at the product level will be tracked by the PO during sprint review – Scrum.org

  2. A: “At any point in time in a Sprint, the total work remaining in the Sprint Backlog can be summed.
    The Development Team tracks this total work remaining at least for every Daily Scrum to project
    the likelihood of achieving the Sprint Goal. By tracking the remaining work throughout the
    Sprint, the Development Team can manage its progress.”