You manage a development team that uses the Microsoft Visual Studio Scrum 2.0 process template.
You establish a product backlog, allocate backlog items for a sprint, and define the tasks required to complete the sprint.
You need to ensure that the agreed upon work is assigned to team members.
Who should be responsible for assigning work to team members?
A. Team members
B. Product owner
C. Scrum master
D. Team lead
Correct Answer: A
Explanation/Reference:
* In Scrum, work should never be directed or assigned. When creating or updating a task, don’t assign it to anyone who doesn’t request the work.
* With sprints defined, team members can assign work items to current or future iterations.
Professional Scrum Development with Microsoft Visual Studio 2012 p.183