Your Scrum team is planning a release and wants to prioritize user stories based on value and risk.
The stories are grouped according to the ratio of value to risk, as shown in the following image. Effort is the same for all user stories.
The product owner on your team wants to ensure a higher return on investment based on today’s prioritization activity.
You need to prioritize these user stories into four sprints for this release.
Use the drop-down menus to select the answer choice that answers each question.
Hot Area: