A company has been running off replicated, business-critical VMs at their disaster recovery location since an earthquake near the primary data center occurred. Since the threat has passed, they want to stop the replicas and switch to the VMs at the primary data center without losing data. Which of the following actions is the first step they should take?
A. Failover
B. Permanent failover
C. Commit failback
D. Failback to production
E. Planned failover
F. Undo failover
The anysware is D. Failback to production. The Planned Failover has already been executed in the moment that they switch to the dr site. They want to move back to primary site (Failback to production)
D. Failback to production
E – Planned Failover