An administrator has two clusters: Site A and Site B.
Async DR is configured between the clusters as follows:
Site A is the Primary Site
Site B is the Secondary inactive Site, no VMs running
Site A is fully in Production
Site B used as Backup/Disaster Recovery
The customer wants to perform a planned failover between the sites. How should the administrator accomplish this?
A. Click Activate on the Secondary site within the Data Protection Dashboard
B. Click Activate on the Secondary site and run deactive NCLI command on Primary site
C. Choose Migrate on the Secondary site within the Data Protection Dashboard
D. Choose Migrate on the Primary site within the Data Protection Dashboard