An administrator has a scheduled policy that backs up 20 clients, each with multiple mount points and multiple streams enabled. One of the jobs has failed and is in an Incomplete state. How should the administrator verify the incomplete job runs prior to the next scheduled backup?
A. run a manual job for the client
B. resume the gob
C. run a manual job for the mount point
D. resume the parent job