There is a requirement for a business process diagram to have two subsequent activities routed to the same user. During a demonstration, a business user notices that upon completing the first task they must return to their inbox to start the next task. The business user would prefer to have the second task automatically appear upon completion of the first task and asks the BPM application developer what options are available. How should the BPM application developer respond? This can be configured by:
A. making a change to the 100Custom.xml file.
B. changing the first activity’s routing to "Last User in Lane".
C. changing the second activity’s routing to "Last User in Lane".
D. changing the implementation of the activity and selecting the "Automatically flow to next task" check box.