Identify THREE items that would be part of the work-breakdown structure showing the key testing activities for the acceptance test project.
A. Test planning, test case preparation and test execution for each of the four iterations
B. Work should be explicitly allocated to test completion, test management, installation and to training on using the system
C. Activities to deploy the system in the user environment
D. Regression testing in the second, third and fourth iterations
E. Development activities for unit and integration testing
F. Reviews on requirements documentation
G. Defining test environment requirements for system testing