In a Procurement implementation, your customer has a requirement for a given business unit to enable "funds check” on purchase orders. This requires that budgetary control be enabled.
What configuration must you complete to enable budgetary control in that business unit?
A. Enable budgetary control in both the Configure Requisition Business Function and Configure Procurement Business Function by selecting the business unit in scope.
B. Enable budgetary control by selecting the business unit in scope using the task Configure Procurement and Payables Options.
C. Enable budgetary control by selecting the business unit in scope using the task Configure Procurement Business Function.
D. Enable budgetary control by selecting the ledger and business unit by using the task Manage Budgetary Control.
Correct answer is D. There is no budgetary control option in Common Options for Payables and Procurement.