What is the adjustment action that should be applied on this expenditure item?

An employee has entered eight hours of billable time on a project. You want only three hours to be billable and five hours to be nonbillable. What is the adjustment action that should be applied on this expenditure item?
A. Transferthe item.
B. Change the billable status.
C. Split the item.
D. Apply billing hold.
E. Change quantity.