What is the status of the pipeline runs?

You have an Azure Data Factory instance that contains two pipelines named Pipeline1 and Pipeline2.
Pipeline1 has the activities shown in the following exhibit.

Pipeline2 has the activities shown in the following exhibit.

You execute Pipeline2, and Stored procedure1 in Pipeline1 fails.
What is the status of the pipeline runs?
A. Pipeline1 and Pipeline2 succeeded.
B. Pipeline1 and Pipeline2 failed.
C. Pipeline1 succeeded and Pipeline2 failed.
D. Pipeline1 failed and Pipeline2 succeeded.