During a Sprint Planning, a team has picked three User Stories:
Story 1 – 5 Story Points
Story 2 – 8 Story Points
Story 3 – 3 Story Points
At the end of the Sprint, the team has completed Story 1 and Story 3 and the Product Owner accepts these. The team has almost completed Story 2 but there are a few bugs identified in acceptance tests.
What is the Velocity of this team?
A. 8 points
B. 16 points
C. 12 points
D. Insufficient information given – it depends on % completion of Story 2