You develop a SQL Server Integration Services (SSIS) package in a project by using the Project Deployment Model. It is regularly executed within a multi-step SQL Server Agent job.
You make changes to the package that should improve performance.
You need to establish if there is a trend in the durations of the next 10 successful executions of the package. You need to use the least amount of administrative effort to achieve this goal.
What should you do?
A. After 10 executions, in SQL Server Management Studio, view the Execution Performance subsection of the All Executions report for the package.
B. Configure the package to send you an email upon completion that includes information about the duration of the package. After 10 executions, view the emails.
C. Enable logging to the Application Event Log in the package control flow for the OnInformation event. After 10 executions, view the Application Event Log.
D. Enable logging to the Application Event Log in the package control flow for the OnPostExecute event. After 10 executions, view the Application Event Log.