What will you recommend?

During reorganization, two cost centers are merged, and all future postings should go to only one of them. If postings are made to the wrong cost center in future FI-postings, your customer wants to ensure that the wrong cost center is automatically replaced by the correct one.
What will you recommend?
A. Define two substitutions for the Line Item call-up point.
B. Define a substitution in FI with the wrong cost center as a prerequisite and the correct one as the substituted value.
C. Create a user-specific program to substitute the wrong cost centers automatically overnight.
D. Define a validation in CO to ensure that the functional area is filled in the cost center master.

Download Printable PDF. VALID exam to help you PASS.