A business analyst working on a project has identified:
3 requirements for which there is a workaround and the users can live without;
2 requirements that the users can live without for now;
15 requirements which, if not delivered, will make the solution unworkable or useless.
When these requirements are prioritized using MoSCoW, which of the following categories will not be used?
A. M
B. S
C. C
D. W
Should be option C, Could