Which action must be performed to finish the installation?

You are installing a DL385 GEN10 LFF server at a customer site. The customer has a P8i6i-a RAID controller in the host After installing the provided 8 LFF disks in the front drive Days, you realize that the order also included two more SFF drives for the OS to boot from, but there are no SFF drive slots in the server, because it shipped from the factory.
Which action must be performed to finish the installation?
A. Order the optional Premium 6 SAS/SATA+2 NVMe cage to house the two SFF drives.
B. install the two SFF drives in the two included SFF slots in the universal Media Bay.
C. Give the two SFF drives to the customer to keep on-site in case of future drive failure.
D. Order the optional 2-SFF rear drive box to house the two SFF drives