Which approval level deploys a resource but withholds access until approval is granted?
A. The pre-request level
B. The pre-approval level
C. The post-approval level
D. The post-request level
Which approval level deploys a resource but withholds access until approval is granted?
A. The pre-request level
B. The pre-approval level
C. The post-approval level
D. The post-request level