Which contains the minimum required steps to move the observer to host2?

The Oracle database 12c Observer is currently running on host1 and you wish to have it running on host2.
Examine this list of possible steps:
1) Stop the observer on host1.
2) Disable Fast-Start Failover.
3) Update the broker configuration with the new observer hostname.
4) Enable Fast-Start Failover.
5) Start the Observer on host2.
Which contains the minimum required steps to move the observer to host2?
A. Execute only task 5.
B. Execute tasks 1, 3, and 5.
C. Execute tasks 1, 2, 3, 4, and 5.
D. Execute tasks 1 and 5.