A production database has the following daily midnight backup schedule which includes all table spaces. The database incurs the same volume of daily activity (inserts, updates, and deletes).
Sunday – Delta
Monday – Incremental
Tuesday – Delta
Wednesday – Delta
Thursday – Incremental
Friday – Delta
Saturday – Full
Which day would you expect a RECOVER DATABASE following that day’s backup to take the longest time to complete?
A. Friday
B. Monday
C. Saturday
D. Wednesday