Two office buildings are connected via copper network cabling buried in the ground. During local construction, the second building suffers a permanent network outage.
Which of the following are MOST likely the causes of the outage? (Select two.)
A. Crosstalk
B. Open circuit
C. Short circuit
D. Signal attenuation
E. Electromagnetic interference
Exam N10-008: CompTIA Network+Free dumps for N10-008 in PDF format.High quality N10-008 PDF and software. VALID exam to help you pass. |
According to CompTIA Net+ the answer is B. Open circuit and E. Electromagnetic interference