A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
A. Project team members
B. Project sponsor
C. Project manager
D. Project scheduler
A WBS is being developed for a project.
Which of the following would be BEST suited to contribute cost and time estimates for the project activities?
A. Project team members
B. Project sponsor
C. Project manager
D. Project scheduler
Agree with you guys
One of the unwritten rules is: “You never task the Sponsor with work”
Yeah, I tend to agree here, the Project Sponsor is not the best for this. Something is fishy here with some of the questions and answers…
The answer should be A.
“Project team members are responsible for a number of activities on the project. One of
their most important duties is contributing deliverables according to the schedule. A
partial list of other duties may include the following:
-Time and duration estimates for the tasks they are working on
-Cost estimates for deliverables or other project work purchased from outside the
organization”
Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 85