Testing effort can depend on a number of factors, which one of the following is MOST likely to impact the amount of effort required?
A. The predicted number of defects and the amount of network required
B. The ratio of developers to testers in the project team
C. The planned use of a project management tool to schedule tasks
D. The responsibilities for testers and developers being clearly defined