Home » Oracle » 1z0-982 » Which statement is true when configuring the Projects option?
Which statement is true when configuring the Projects option?
A. If using the Projects option, then the Capital option and the Workforce option must be configured
B. If using the Projects option, there is no dependency with the Capital option.
C. If using the Projects option, then the Capital option must also be configured.
D. If using the Projects option, then the Capital option must also be configured, only if capital projects are enabled.
Correct Answer: D
Explanation/Reference:
Optionally, for capital projects, you can allocate project expenses either partially or in full to one or more assets.
References:
Oracle Cloud, Administering Planning for Oracle Enterprise Planning and Budgeting Cloud, page 5-1 https://docs.oracle.com/cloud/latest/pbcs_common/EPBUG/
EPBUG.pdf