Which step should be taken by the administrator to meet this goal?

A host in the cluster experiences a permanent NIC failure, and the replacement part will not arrive until the next morning.
The administrator needs to ensure the availability of the production workload at all times.
Which step should be taken by the administrator to meet this goal?
A. Shut down the production VMs.
B. Perform a live vMotion to another host.
C. Disable the vSAN Service on the VMkernel port.
D. Enter Maintenance Mode with “Full Data Migration”

microsoft-exams

0 thoughts on “Which step should be taken by the administrator to meet this goal?

  1. Answer : D

    vSAN evacuates all data to other hosts in the cluster and maintains the current object compliance state.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.