Which three actions are scheduling requirements?

You assign resources to a project.
You need to define the scheduling requirements for the project.
Which three actions are scheduling requirements? (Each correct answer presents part of the solution. Choose three.)
A. Setting up the calendar to use for the workers on the project
B. Specifying the estimated hourly rate for the workers on the project
C. Specifying the type of calendar for the project
D. Setting the start date and end date of the project
E. Specifying the estimated number of worker hours required to complete the project