You finished a new installation and executed Config Advisor successfully. You review the physical racking and cabling on one of the controllers, and notice an amber light that was not previously on. Which two actions should you perform before you turn over the cluster for production? (Choose two.)
A. Remove cables connected to the controller until you find the one responsible for the controller issue.
B. Review AutoSupport messages which could explain the controller state.
C. Execute Config Advisor again to check for new errors.
D. Let the customer know the cluster is operating normally while the amber LED is on.