Which two statements describe the relationship between a window, a resource plan, and a job class?
A. A window specifies a resource plan that will be activated when that window becomes active.
B. A window specifies a job class that will be activated when that window becomes active.
C. A job class specifies a window that will be open when that job class becomes active.
D. A window in association with a resource plan controls a job class allocation.
E. A window in association with a job class controls a resource allocation.
Correct Answer: AE
Explanation/Reference:
Explanation:
Windows work with job classes to control resource allocation. Each window specifies the resource plan to activate when the window opens (becomes active), and each job class specifies a resource consumer group or specifies a database service, which can map to a consumer group. A job that runs within a window, therefore, has resources allocated to it according to the consumer group of its job class and the resource plan of the window.
Reference: http://docs.oracle.com/database/121/ADMIN/schedover.htm#ADMIN12366