You have scheduled item publication to a spoke system with specific item publication criteria and the following details:

You have scheduled item publication to a spoke system with specific item publication criteria and the following details:
Day 1: First publication date to the spoke system with a publication schedule that runs every five days
Day 5: Next schedule process
Day 10: Next schedule process
Day 15: Next schedule process
On Day 12, your customer decides to publish from Day 6.
Identify the parameters that are required to run this request and the data set that would result from this request.
A. Set Last Publication Date as Day 6, which will publish all records updated from Day 6 up to Day 10.
B. Set Last Publication Date as Day 1, which will publish all records updated from Day 6 up to Day 12.
C. Set Criteria Date as Day 6, which will publish all records updated from Day 6 up to Day 10.
D. Set Criteria Date as Day 6, which will publish all records updated from Day 6 up to Day 12.

Download Printable PDF. VALID exam to help you PASS.

Leave a Reply

Your email address will not be published. Required fields are marked *


The reCAPTCHA verification period has expired. Please reload the page.