Weekly full backups run for clientA on master1 using a storage unit that belongs to media1. The administrator is required to retain clientA’S full backups for a period of four months. When the administrator modifies the full schedule, an option for 4 months is missing from the Retention drop-down list.
How can the administrator add a four-month retention?
A. modify an existing retention level in the mater server host properties, under Retention Periods
B. ignore the selection list and type in the desired retention period directly
C. add a new retention period in the media server host properties, under Retention Periods
D. increase the Image cleanup interval in the master server host properties, under Clean-up