How many jobs go Active when the job is started, excluding parent jobs, assuming there are enough storage resources to handle the expected jobs?

An administrator has a backup policy with the following policy attributes:
• 3 paths listed in the Backup Selections list
• 5 clients listed in the Clients list
• Allow multiple data streams is selected
• Limit jobs per policy is set to 4
How many jobs go Active when the job is started, excluding parent jobs, assuming there are enough storage resources to handle the expected jobs?
A. 3
B. 4
C. 12
D. 15

Download Printable PDF. VALID exam to help you PASS.

2 thoughts on “How many jobs go Active when the job is started, excluding parent jobs, assuming there are enough storage resources to handle the expected jobs?

  1. Correct answer is B.4 as it asked how many will go active at once excluding the parent job which is 4