Home » Amazon » AWS Certified Advanced Networking - Specialty » How many LOA documents have been requested and completed for this configuration?
Your company has a highly-available Direct Connect solution that utilizes two datacenters. Each datacenter was initially configured with one four-connection LAG and one standard DX connection. How many LOA documents have been requested and completed for this configuration?
A. 1
B. 4
C. 2
D. 10
Correct Answer: B
Explanation/Reference:
Only one LOA document is required for each physical connection. The logical connections in the LAG do not need separate LOAs, but they do have separatepages.
2 X 4 (Lags)+2 X 1 Standard DX= 10
LAGs are physical connections bundled together