How would the BPM analyst adjust the diagram to capture this requirement while adhering to best practices for proper process modeling granularity?

A BPM analyst has built the following process diagram during a process discovery workshop.


Each activity noted above will have a separate Coach displayed in IBM Business Process Manager V8.0. How would the BPM analyst adjust the diagram to capture this requirement while adhering to best practices for proper process modeling granularity?
A. Combine the Developer’s 3 activities into a sub-process.
B. Add a separate swimlane for each activity in the Developer swimlane.
C. Add a separate milestones for each activity in the Developer swimlane.
D. Color each activity with a different color to indicate separate Coaches.