The Total Spending Plan Tally for a project is the sum of the Spending Plans assigned to____.
A. each project in the Enterprise Project Structure (EPS)
B. each Work Breakdown Structure (WBS) element in the project
C. each immediate child Work Breakdown Structure (WBS) element
D. each immediate parent Work Breakdown Structure (WBS) element