You are a Project Manager who is closing out a completed project. You have confirmed that all hours that should be charged to the project have in fact been charged. You have conducted your Lesson Learned activity. All parties agree that the project is complete.
Which project status is the best choice for this project?
A. Active
B. Inactive
C. What-If
D. Planned